
As concrete dries and shrinks it wants to crack somewhere. Joints cut at the right time and spacing make that crack form along a straight line instead of at random.
Why joints are cut
Concrete loses volume as it hardens and dries. This shrinkage creates stress that is released as a crack somewhere. A cut joint gives that crack a prepared line. The CIP 6 guide of the US National Ready Mixed Concrete Association (NRMCA) therefore describes joints as pre-planned cracks.
At early ages and as it dries
According to the same guide, concrete is weak in tension, and if its shrinkage is restrained and the tensile stress exceeds its strength, it cracks. Most early cracking, before the concrete dries out, is caused by temperature changes or by the slight contraction that takes place as it sets. As the concrete dries it shrinks further, and new cracks may form or existing ones may widen.
Three types of joint
Contraction joints create weakened planes in the concrete that determine where cracks will occur. Isolation joints separate the slab from structural elements such as walls, footings and columns and allow independent movement. Construction joints are the surfaces where two separate pours meet; they usually form at the end of a day's work, and their locations are planned in advance.
Timing
Cut too early and the edges ravel; cut too late and the slab cracks on its own first. According to CIP 6, early-entry dry-cut saws generally run 1 to 4 hours after finishing is complete, while conventional saw cuts are made within 4 to 12 hours after finishing. If the edges ravel during sawing, the cut is delayed, but waiting too long increases the risk of uncontrolled cracking. The guide stresses that timing depends on the setting characteristics of the concrete; in cold weather setting slows down, so sawing may come later (cold-weather concreting).
Depth of cut
The guide recommends that the groove of a contraction joint be at least a quarter of the slab thickness deep and not less than 25 mm. Joints made with early-entry saws are shallower than conventional cuts but should still be at least 25 mm deep. On a 160 mm slab, for example, this means a cut of about 40 mm.
Joint spacing
Joint spacing is designed according to slab thickness and concrete properties. CIP 6 gives a maximum spacing of 24 to 36 times the slab thickness; for a 100 mm slab that is about 3 m, and the guide recommends that spacing should not exceed 4.5 m. On industrial floors, the joint layout is set together with the structural design (industrial concrete slab).
Panel shape
The panels formed by the joints should be square or nearly so; according to the guide, the length should not exceed 1.5 times the width. L-shaped panels are avoided. The cutting plan is drawn before the pour, and the joint locations and sawing times are decided before construction.
Columns and corners
Stress concentrates around columns and at re-entrant corners, so the joint layout needs extra thought there. The guide recommends leaving circular or square openings around columns, to be filled after the floor has hardened. A square opening is turned at 45 degrees so that the contraction joints meet at the corners of the square.
Mesh and construction joints
According to the guide, alternate wires of the mesh are cut at contraction joints, or preferably the mesh is discontinued across the joint; mesh does not prevent cracking, it keeps cracks closed. Keyed construction joints are not recommended for industrial floors; slabs carrying heavy loads use dowels, which must be aligned parallel to each other.
Joint filling
Where forklifts run, a suitable joint filler protects the edges; the guide asks for joints in heavily trafficked industrial floors to be filled with a material capable of supporting the joint edges. This also extends the life of any coating applied later. We cover sealant dimensions in joint and crack repair and loads in racking and floor loads.
Hardeners and coatings
On slabs with a surface hardener the sawing schedule is even tighter (concrete surface hardeners). If the floor is to be coated later, contraction joints keep their place in the coating too; you can see how joints are built into the preparation plan on our epoxy surface preparation page (power-floated screed).
Frequently Asked Questions
When are concrete joints cut?
Once the concrete can take the saw but before it cracks on its own; according to NRMCA CIP 6, about 1–4 hours after finishing with early-entry saws and 4–12 hours with conventional sawing.
What if joints are not cut?
Shrinkage stress makes the slab crack at random, and these cracks can later show through a coating.
Should joints be filled?
Where forklifts run, a suitable filler capable of supporting the edges is recommended to protect them.
How deep should a joint be cut?
At least a quarter of the slab thickness and not less than 25 mm; joints made with early-entry saws should also be at least 25 mm deep.
Would you like a site survey for your floor? HBK Epoxy Flooring, based in Gaziantep, offers free surveys and quotations in the surrounding provinces.
0507 597 9537 WhatsAppRelated articles

Screed vs Concrete: What Is the Difference and Where Is Each Used?
Concrete is a load-bearing building material; screed is a layer that levels the surface that will receive a floor finish. Their mixes, their roles and the checks needed before coating are different.
Read article ›
Pouring Concrete in Cold Weather: What Temperature, and How to Protect It
Concrete can be poured in winter; what matters is not the air but the temperature of the concrete and keeping it from freezing until it gains strength. TS 1248 sets the rules.
Read article ›
Choosing Stamped Concrete Patterns and Colours
Two things define how stamped concrete looks: the stamp pattern and the colour. The right choice depends on use, architecture and surrounding materials.
Read article ›
